Pipeline - Main Control Centere, Sub-Control CenterOil and LPG transportation, 6 pipelines, each >500 km,
Algeria.
Siemens scope of supply:
 |
SCADA system; |
 |
SINAUT remote transmission units along the pipelines; |
 |
fiber optic transmission system; |
 |
fiber optic cable; |
 |
uninterruptible power supply; |
 |
passive cooling shelters; |
 |
cathodic protection monitoring. |
|
| |
|
|
| |
|
|
 |
|
Pipeline - Main Control Centere, Sub-Control CenterNatural Gas Pipeline, 540 km/48 inch, Sumatra Island,
Indonesia.
Siemens scope of supply:
 |
redundant SCADA system with independent back up systems at 3 stations; |
 |
integrated leak detection and line balancing; |
 |
management information system (MIS); |
 |
remote transmission units; |
 |
integration of various subsystems via Modbus; |
 |
telecommunication systems. |
|
| |
|
|
| |
|
|
 |
|
Pipeline - Main Control Centere, Sub-Control Center
Revamp of Tennessee Gas Pipeline 100, Louisiana, Mississippi,
Kentucky and Tennessee.
Siemens scope of supply:
 |
6.6-MW and 7.5-MW motors; |
 |
13.8-kV switchgear, substations; |
 |
25-MVA transformers; |
 |
SIMATIC PLC automation system; |
 |
low-voltage MCCs. |
|
| |
|
|
| |
|
|
| |
|